|
| |

|
10- Electricity and Gas
Tunnels |
|
Subterranean Sydney |
| |
TUNNEL UNDER THE HARBOUR
The only tunnel connecting the two sides of Sydney Harbour is now
flooded and virtually forgotten. It was built between Long Nose Point,
Balmain, and Manns Point, Greenwich, from 1913 to 1924 to carry submarine
electricity cables for the electric tramway system on the north side of the
Harbour. Submarine cables laid across the harbour earlier had suffered
damage from ships dragging their anchors.
The tunnel was flooded about 1930, whether intentionally to avoid
continual pumping or as the result of a sudden inrush of water is not clear
from the records. The cables in the flooded tunnel remained in use until
1969, but are no longer used because ample supplies of electricity are
available on the north side of the harbour from Electricity Commission
substations. The tunnel may one day be pumped out to recover the valuable
copper in the cables.
When it was built, the tunnel was one of Australia's major
engineering feats. Here is how a reporter from, the Sun described his
journey under the harbour in 1924:
There is not much outward evidence of this great work. At the Long
Nose Point there is the usual pit-head working and-the mouth of the tunnel.
At the Greenwich side there are two openings. A shaft nearer the water,
which descends directly down into the bowels of the earth, and further up
the hill, another opening where the slope downward commences.
The atmosphere was cool and pleasant, electric light bulbs twinkled
like golden glow worms, and here and there the water trickled slowly in from
the roof and sides; in one or two places outlet pipes discharged a flow of
percolated water into the bed of the tunnel. A little light railway ran
right through, at odd spots few men worked putting the finishing touches to
a job which they talk of with pride. Running the length on one side were
cement racks to hold the high tension wires which will supply electric power
for trams and trains on the north side of the harbour. At one end was a pool
some six feet in depth, where the soakage collects, and is pumped to the
surface. ...
The tunnel is perfectly straight, except at Greenwich Point, where it
takes a bend to allow an outlet at a suitable spot. From outlet to outlet it
measures 1,760 feet. At each shaft it descends steeply into the ground at a
grade of 2 in 1, except in a section at the Greenwich end; where a steep cut
had to he made to avoid trouble. Here the grade is 1 in 1.3.
On the level of the tunnel it is possible to walk upright with ease.
In fact, two or three men could walk abreast, and there is ample room for
any working party to repair the cables.
The construction job itself was, according to the Sun reporter, a
series of "Homeric battles":
At the commencement of the work, the necessary compressor was located
on the south 91to supply power for the pneumatic drills. Work was started
from three points -Long Nose Point, Greenwich, and a shaft at the extreme
end of Mann Point, which is a continuation, more or less, of Greenwich.
Progress was rapid for a while -about 25 yards per month at every point. But
then came problems. First of all, the residents of Long Nose Point, in
letters and protests very much to the point, caused the
abandonment of the Long Nose end after a considerable distance had
been excavated. Work, therefore, went slowly on from the north side until
about May, 1915, when a big fissure in the rock about the middle of the
Parramatta River was met. The only solution was to seal up the tunnel and
patch the fissure. A bulkhead was built into the tunnel to stop the progress
of the sand, water and silt, and a staging was built in the middle of the
river and drills were bored through the riverbed. With great accuracy these
entered the tunnel almost in the centre. Then pipes were entered through the
holes, and a cement mixture was gradually pumped into the tunnel about the
vicinity of the fissure.
The cement pumping operation was repeated through three other pipes
in line with the original ones, and the tunnel was sealed twice and allowed
to set. The door was then re-opened, and the silt and sand removed. It was
then found that the second sealing showed signs of weakness, and it was
thought advisable to abandon the top tunnel and go deeper into the rock. A
permanent bulkhead was built into the rock and the tunnel was sealed up with
about 15 feet of concrete, and it remains like that today.
Then a second tunnel was commenced 50 feet below the first one. The
down grade was increased to 1 in 1.3. The work was still being carried out
with explosives, and progress was fairly fast; but on arrival at the point
immediately below the original break-in, another crevice was struck, and
water rushed in. On this occasion, the engineer in chief,
R.L. Rankin and the resident engineer, W.R.H. Melville, decided to go
with the foreman and have a look at the fissure that had flooded the tunnel.
Placing candles on pieces of wood, they swam about 40 feet into the centre
of the tunnel. It was a risky job. The surface of the water was less than a
yard from the top of the tunnel. If the inflow had suddenly increased, they
would have been caught like rats in a trap.
The break-in was later sealed by placing 6-inch pipes, about 15 yards
long, into the crevice, and the whole of the tunnel in the immediate
vicinity was packed with bags of clay, tightly rammed. In front of this was
placed a steel bulkhead with a steel door, and through the bulkhead
three-inch pipes were laid right into the crevice, to allow the water to get
out. Through the 6-inch pipes cement was pumped until finally it was not
possible to shoot any more into the crevice under very heavy pressure. This
was allowed to set for about three months, when the bulkhead door was
opened, and sufficient of the bags of clay removed to allow the men to reach
the crevice, when they found that the inflow had practically stopped. The
bags of clay were completely cemented together.
A detour was cut at this point to about 6 feet, to get round the
crevice, and when the men had passed it they worked back to the original
line of excavation.
The section of the tunnel that had been sealed up was cut through,
the detour filled in, and the original straight line of excavation restored.
After going about 50 feet past the crevice, they struck another small
fissure, which was apparently a section of the original one, and water
suddenly flowed in at the rate of about 2400 gallons an hour. This was not
sufficient to stop the progress of the work, but pumps were installed to
cope with the inflow.
Soon after the men began to work on the up-grade, and here great care
had to be exercised to prevent the material falling back on them. The
material was cut out by channelling machines, which allowed it to be removed
without difficulty. Eventually -it was a great moment -the men broke
through. Away in the distance they could see a tiny gleam of daylight. It
was the opening at the Long Nose Point side. Their calculations had been
made with remarkable accuracy. The centre line, when the tunnel was
connected, was only an 1/8th of an inch out, while the levels were
absolutely correct.
BEHIND THE GREEN DOOR
If You have ever noticed street corner pillar boxes painted Sydney
County Council green,
YOU may have vaguely imagined they were some kind of large fuse
boxes. But, in fact,
behind the green doors lie another part of subterranean Sydney.
Unlock the door of a pillar box and you will find a hole in the
ground below street level
big enough to take a couple of men and a large power line which the
SCC calls a low voltage distributor.
Sydney's electricity comes mainly from Vales Point near Newcastle. It
travels in high voltage form to reduce the amount of electricity lost in
transit. When it reaches Sydney it goes to substations which break it down
from 33,000 to 11,000 volts. One such substation is located at Lincoln
Street, Woolloomooloo, which is also the start of the SCC's only tunnel
still in use. There is one under the Harbour from Long Nose Point, Balmain,
to Greenwich on the north shore, but this is flooded and is no longer used.
To inspect the Woolloomooloo tunnel one needs special permission from
the SCC -and a torch. Most of the light bulbs in the tunnel are out of
action. The tunnel itself is a fairly roomy cement affair built in the
1950s. For most of its length it is dry but in a couple of places water has
seeped through and is beginning to create small stalactites from the cement
roof. It would cost a fortune to build today and it is unlikely that more
like it will be built.
.jpg)
An electricity cable being pulled in Kent Street, City, in the 1930s.
It carried cables armoured with steel on the outside and wrapped in
lead sheath and paper insulation. You can put your hand on the outside of
the cable with no ill effect. It feels slightly warm from all the energy
deep inside the copper core. The cables have been there for thirty years and
are in good shape.
After walking about a kilometre through the tunnel under the Cahill
Expressway, one comes out through a green door into the Domain just below
the Art Gallery, and stands blinking in the sunlight. From this point the
cables go through concrete underground ducts to smaller substations in the
city. After removing the manhole covers at the corner of Phillip Street at
Martin Place, you can climb down ladders to about fifteen metres below
street level. This is the SCC's biggest and deepest pit. It was built as
part of the relocation of ducts during the construction of the Eastern
Suburbs Railway. There are empty ducts waiting to take a large number of
mains in the future. Digging under central Sydney is becoming increasingly
difficult and the Eastern Suburbs Railway is probably the last big excavation that will take place there.
By lifting part of the new paving sections in Martin Place you can
climb down to inspect the substation that supplies most of the central
banking system of Sydney. If the power fails here, then the computers of
most of Sydney's head offices stop too. So the board has not one but three
transformers. Any fault in the system is reported by an automatic signalling
system and shows up on the mosaic board at the SCC headquarters in Goulburn
Street. When a fault is reported by a customer, the SCC will isolate the
distributor and, if possible, bring supply round by an alternative route to
the customer while they fix the fault. The SCC takes great pride in
maintaining its service to customers, and workmen in suitably insulated
clothing and shoes actually carry out the repairs to Direct Current
distributors while the wires are still live. Direct Current is only used to
supply a few old buildings around Chifley Square which have lifts needing
this form of current. They are being gradually phased out and should soon be
gone much to everybody's relief.
When working in the cramped spaces below street level while repairing
low voltage distributors, workmen welcome the sight of cockroaches. Their
presence shows that there is plenty of oxygen -an important consideration
when you are welding wires in a confined space below ground where there
could be gas. Not so welcome are the rats which persist in chewing through
low voltage cables, particularly around the Opera House. This has a fatal
effect on both rats and cables. Another hazard to the electric supply are
con-. tractors excavating foundations for city buildings. Nobody has been
killed for about ten years, but this is mainly thanks to the SCC signalling
system rather than the care taken by the excavation workers. The signalling
system automatically cuts off supply before it can travel through the
offending machine and kill the operator. The heat from a main is SO great
that it can melt a mechanical digger's shovel in a few seconds. A third
hazard is water and, given Sydney's occasional downpours, not even the
stoutest pump and the 'largest drainage system could hope to deal with this
problem completely.
Electricity authorities have been digging up Sydney to lay cables
since 1903. In that year, the Electricity Undertaking of the Municipal
Council of Sydney began building the Pyrmont Power Station and excavating
over forty kilometres of trenches to link the station with the Sydney Town
Hall and Darlinghurst. They also dug a tunnel from the Power Station to the
nearby Harbour to provide cooling water. The Power Station is now used as a
museum but the tunnel is still there.
The official switching on ceremony took place at the Pyrmont Power
Station on 8 July 1904.
"City Blast Scare" screamed the headline in the Sun on 19 April 1977.
"Fire Rages Under City Building" shouted the Mirror from the street corner.
The Sydney evening Papers are famous for never letting the facts interfere
with a good story. By the next day when the whole thing had simmered down,
the Sydney Morning Herald reported soberly: ''Gas Main Fire Stops City
Traffic". It went on to give details of how a cigarette butt combined
.jpg)
Pulling electricity cables through ducts over a bridge built over the
Warringah Expressway at West Street, Naremburn, in the 1970s.
with a gas leak had started a fire at a broken gas main at the corner
of Elizabeth and Park Streets. In the words of the famous headline, it was a
small fire and nobody was hurt.
It is not the sort of publicity the gas authority seeks out. But it
does serve as a reminder of the huge network of gas pipes beneath our city
streets and the patient and normally unpublicised work of the engineers and
company staff who put them there.
Although gas pipes are normally laid in trenches rather than large
tunnels, the Australian Gas Light Company can fairly claim to have some of
the oldest networks of subterranean Sydney. In fact, the gas company has
been digging up Sydney streets for well over a hundred years.
The company was given a Royal Charter in 1837 and charged with the
responsibility of lighting Sydney's gloomy streets. It turned on the lights
on 24 May 1841 to celebrate the birthday of Queen Victoria. The sites for
its first gas holder tanks had to be hewn out of solid sandstone at Darling
Harbour. By 1925,fthe company could proudly claim to be the seventh largest
gas undertaking in the British Empire.
Its Mortlake Works supplied gas consumed over an area of 600 square
kilometres and piped gas up to 25 kilometres away. Altogether, it had dug
trenches for 6400 kilometres of mains and service pipes. In 1875, the Gas
Act made it possible to set up a gas service on
the North Shore. James Walter Fell imported all the necessary
equipment and set up the first North Shore Gas works at Neutral Bay. By
February 1877, the pipes were laid and the first customers were connected.
Unfortunately the start of the service was delayed by a severe drought. Gas
tanks -geometers as most people still call them -are like huge inverted cups
full of gas sitting on water which keeps the gas in. The trouble was that,
in February 1877, the North Shore had no water! Finally the rain came and
the North Shore gas service was able to start.
The North Shore Gas Company is now merged with its much larger sister
company, the Australian Gas Light Company and together they supply the-whole
of metropolitan Sydney.
.jpg)
An electricity cable pit in Campbell Street, City.
Like most utilities that dig trenches and tunnels under Sydney
streets, the gas company occasionally digs up forgotten bits and pieces of
Sydney's past. One such piece was an old wooden tunnel which came to light
while replacing pipes at Chatswood. Nobody in the gas company knew it was
there. It was made of red gum and filled with sand to stabilise the pipes it
carried inside.
In common with other utilities the gas company has' experienced
problems in getting its services across Sydney Harbour. However, the gas
company has special difficulties because it produces a product that will
cause its pipes to float just below the surface of the water where it would
be a danger to shipping. So the board has encased its pipes in concrete at
Roseville Bridge and the Spit where it crosses Middle Harbour and has done
the same for its pipe under the Parramatta River.
.jpg)
This new pipeline for natural gas was laid at the Australian Gaslight
Company plant at Mortlake in the late 1970s.
The gas company's supplies are normally carried in pipes buried in
trenches. The building of the Warringah Expressway has provided the board
with its only real tunnel to add to the network of walkable tunnels around
Sydney. The tunnel in question begins at Mount Street, North Sydney, where
it goes down for about 10 metres and then continues under the expressway.
The total distance is over 100 metres. As it measures nearly three by three
metres, it is quite big enough to walk through and it provides access for
the Water Board and electricity suppliers who share the tunnel.
The biggest problem faced is one it shares with all other utilities.
There are so many services competing for the limited space under Sydney
streets. Subterranean Sydney, in fact, is already seriously overcrowded and
the situation in central Sydney is getting worse. When digging trenches for
the new pipes needed to supply natural gas in the late 1970s the gas company
found great difficulty in finding vacant space. At the corner of Sussex and
Market Streets, for example, the gas company had to dig through three
streets -the existing one, plus two older ones -before they could find a
place to put their pipes.
Despite what most members of the public think, the utilities do
co-operate with each other. Every time one of them wants a "street opening"
they all meet for discussions and take advantage of the opportunity to carry
out maintenance and repairs to their own pipes. It makes good economic
sense. Up to a third of the cost of a job can be for restoration of the road
surface and the gas company, if not the other utilities, is a private
company with shareholders to think about.
The gas company tests its pipes with air before covering over the
road. But Murphy's Law, which dictates that what can go wrong will go wrong,
operates in the gas industry as well as it does in any other human
undertaking. In the case of the gas company, a small leak found after the
road surface has been restored means that the men have to start digging up
the road once more.
Sometimes the problem of digging up the road is complicated by the
difficulty of finding the streets under which the pipes were originally
laid. Around North Sydney, for example. whole streets were obliterated to
make way for North Sydney Station and later, the
Travelodge Motel. The gas mains are still under there somewhere, but
the old gas company records give their location only by the names of streets
which no longer exist. SO before they can start on repairs and maintenance,
the engineers have to spend time consulting old council street maps to find
where the streets used to be.
|
| |
| This section is based
on the excellent book by Brian and Barbara Kennedy. (Subterranean Sydney
(The Real Underworld of Sydney Town), Reed, Sydney, 1982. ISBN 0 589
50312 X). Copyright Brian and
Barbara Kennedy and Reed Publishing. |
| |
|
|
|